Message from our Golf Course Superintendent


Cameron Smith, Golf Course Superintendent

This week, on The Palms golf course, the team received more rainfall than expected, with over 100mm recorded throughout the week. Despite this, renovation progress remains steady and on track. Greens were dethatched, mowed at 2mm, aerated, and treated with amendments to aid recovery. Tees were dethatched and cleaned, while fairways underwent deep slicer aeration and dethatching. Contractors continued tree removal on holes 16 and 17 and began constructing the rock wall along the lake edge for the new 17th tee and adjoining 16th hole.

On The Pines golf course, foliar fertiliser was applied to tees, green aprons, and fairways, with bunker detailing and fungicide and insecticide treatments completed on greens. Renovation works commenced on the large practice green and hole 21 green, alongside the application of amendments to the new tee on the 10th hole of The Palms golf course.

Next week, foliar fungicide will be applied to greens and general preparation will continue on The Pines golf course. On The Palms golf course, works will include verticutting and topdressing greens, mowing and topdressing tees at 6mm, and continued aeration, dethatching, and clean-up of fairways. Contractors will also progress rock wall construction, install Hydrowick drainage, complete path repairs, and lay new turf on the 10th tees.

 

 

This week, the maintenance team completed the following:

  • Applied foliar fertiliser to tees, green aprons, and fairways on The Pines golf course
  • Completed detail trimming of bunkers on The Pines golf course
  • Applied fungicide and insecticide to greens on The Pines golf course
  • Commenced renovation of the large practice green and hole 21 green on The Pines golf course, in conjunction with renovation works on The Palms golf course
  • Applied amendments to the new tee on the 10th hole of The Palms golf course

The Palms Renovations

Greens

  • Dethatched twice in different directions using the Mardeo scarifier
  • Mown at 2mm in two directions
  • Aerated with hollow tines
  • Applied amendments

Tees

  • Dethatched twice in different directions using the TR50 tractor-mounted scarifier
  • Removed chaff

Fairways

  • Completed deep slicer aeration using the Shockwave unit
  • Commenced dethatching twice in different directions using the Mardeo scarifier units

Contractors

  • Tree contractors removed trees on the 17th hole in preparation for the new tee and hole change planned for next year
  • Commenced rock wall works along the lake edge for the new 17th tee and on the 16th hole

Next week, the following will be addressed:

  • Foliar fungicide will be applied to greens on The Pines golf course

  • General preparation work will continue on The Pines golf course

The Palms Renovations

Greens

  • Greens will be verticut and top dressed

Tees

  • Tees will be mown at 6mm and top dressed

Fairways

  • Deep slicer aeration will continue
  • Dethatching and associated clean-up work will continue
  • Fairways will be spiral cut at 6mm

Contractors

  • Rock wall works will continue along the lake edge on the 16th and 17th holes
  • Hydrowick drainage will be installed in selected fairway areas
  • Concrete grinding and repair works will be undertaken on paths
  • New turf will be laid on the 10th tees

The Pines and The Palms golf courses